Stoneworks Garth Housing Progressing – 5 September 2011

Developments at Stoneworks Garth

Developments at Stoneworks Garth

Progress with building affordable housing at Stoneworks Garth
Progress with building affordable housing at Stoneworks Garth

We are now out of the ground on site at Stoneworks Garth with 7 houses up to floor level. Four of the semi-detached properties are now scaffolded out ready for the arrival and installation of timber frames.

Foul and surface water drainage down the main site road is progressing well and the road should start to take shape in the next couple of weeks. Progress is currently being hampered by the overhead electricity supply cables and substation which are to be re-located by Electricity North west.

The remaining 5 properties are affected by the slurry lagoon which runs down the north western edge of the site. Design work has been completed and our contractors should be shortly bringing in a piling rig to carry out vibro compaction to allow foundation construction.

Full details of the self-build plots should be released to individuals who have registered interest in purchase within the next 2 weeks.

If you have expressed an interest in a self-build plot and do not receive your pack by 19th September 2011 please contact one of the LCT group.

Advertisements

Leave a Reply

Please log in using one of these methods to post your comment:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Google photo

You are commenting using your Google account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

This site uses Akismet to reduce spam. Learn how your comment data is processed.

Categories

%d bloggers like this: